So, some progress...

I attached the 3" PVC pipe to the front of the keel as per the plans. Just need to build it up a bit further and then sand back to a fair shape, but I think it looks pretty decent as far as I've gone up to now. Nice and symmetrical and will look better after rounding edges for glassing.

Image

Also the welder arrived. I'm keen to see if I can fabricate the bow forestay/stem fitting myself. First ever attempt at welding was ok and I did a few test welds.

Image
Image

It actually went better than I imagined and with a bit more practice should be fine.

I cut the parts for the stem fitting already using the angle grinder: 316L stainless. They need a bit of cleaning up. Couldn't get the bend as tight as specified in the plans, but it should still be serviceable. Bending the steel was a challenge but I got very close to the required angle. I plan to file down the pieces and get them ready for welding but before doing that I'll make sure I've had a bit more practice with welding some scrap pieces together first (and then beating them severely with a lump hammer to make sure the welds are truly secure!).

Image

Next jobs will be taping the interior keel joints and fairing up the front of the keel. I'll probably fill the pipe at the front of the keel with lead shot mixed with epoxy eventually - different sizes of shot so it packs better, but no rush with that right now.

And I also ordered the first few sheets of ply from the office (thanks Reid!). They are en route currently. After the keel is done I'll aim to make progress on rudder, centreboard, and centreboard case.

Cheers,

Mick


Completed: FB11 (Designer Evan Gatehouse)
Current Build: VG23 (Designer Jacques Mertens)

Barn Lancaster
Frequent Poster
Frequent Poster
Posts: 60
Joined: Sun Mar 02, 2014 4:17 pm
Location: Preston England
Location: Lancashire,England
Contact:

Re: VG23 New Build

Post by Barn Lancaster »

mhd wrote: Thu Aug 18, 2022 4:39 pm Got the keel together to test how the forward portion of it will fit - plans call for 3" pvc pipe on the leading edge. I'll unstitch and epoxy seal the inside surfaces before putting it back together and starting to do the inner joins.

Plans also call for 500kg (~1100 lbs) of lead ballast. I'll bet that won't be cheap these days, but I will try not to think about that until the hull build is out of the way.

Mick

Image
Hi Mick you need to have a laying of the keel ceremony (includes naming the boat) one of the three ceremonies in the life of a boat ,laying the keel, launch ,decommissioning. Here's Talon's https://www.youtube.com/watch?v=eIcRfuSEmVk

mhd
Frequent Poster
Frequent Poster
Posts: 75
Joined: Tue Feb 15, 2022 10:41 am
Location: New Mexico

Re: VG23 New Build

Post by mhd »

Barn Lancaster wrote: Mon Aug 29, 2022 3:49 pm
mhd wrote: Thu Aug 18, 2022 4:39 pm Got the keel together to test how the forward portion of it will fit - plans call for 3" pvc pipe on the leading edge. I'll unstitch and epoxy seal the inside surfaces before putting it back together and starting to do the inner joins.

Plans also call for 500kg (~1100 lbs) of lead ballast. I'll bet that won't be cheap these days, but I will try not to think about that until the hull build is out of the way.

Mick

Image
Hi Mick you need to have a laying of the keel ceremony (includes naming the boat) one of the three ceremonies in the life of a boat ,laying the keel, launch ,decommissioning. Here's Talon's https://www.youtube.com/watch?v=eIcRfuSEmVk
Good point! We have some friends coming over in a couple of weeks - that will be a perfect opportunity! Cheers, Mick
Completed: FB11 (Designer Evan Gatehouse)
Current Build: VG23 (Designer Jacques Mertens)

mhd
Frequent Poster
Frequent Poster
Posts: 75
Joined: Tue Feb 15, 2022 10:41 am
Location: New Mexico

Re: VG23 New Build

Post by mhd »

A batch of plywood and various other bits and pieces arrived earlier this week (thanks Jeff/Reid). I cut the centreboard to shape (will be 3x 3/8" epoxied) and have been cutting lead for ballast. Lead was left over from some roof work last year.

I'll cut out a central oversized cavity in the centreboard, fill with compresses/flattened lead to the specified weight (lead is currently in the garage being squeezed flat under all my G clamps), and completely encapsulate the lead sandwich in the cavity. This will saves melting lead, although that will be unavoidable for the keel ballast in future.

Image

After that will be rounding the edges of the outside pieces, shape the profile, and then epoxy/biaxial over the top.

Cheers,

Mick
Completed: FB11 (Designer Evan Gatehouse)
Current Build: VG23 (Designer Jacques Mertens)

Jeff
Site Admin
Site Admin
Posts: 8037
Joined: Fri Apr 29, 2016 12:17 pm
Location: Vero Beach

Re: VG23 New Build

Post by Jeff »

Nice work Mick!! Thank you for the kind words!! Jeff

mhd
Frequent Poster
Frequent Poster
Posts: 75
Joined: Tue Feb 15, 2022 10:41 am
Location: New Mexico

Re: VG23 New Build

Post by mhd »

Sidetracked with visitors for the past couple of weeks. Today I was back to it and taped the first two interior joints on the keel (9oz biaxial). Will aim to do the rest tomorrow.

Image

And glued the first two layers of the centreboard with epoxy/wood-flour. Layers of lead encapsulated in pure epoxy after some work with 60 grit sandpaper on the lead and ply. The lead layer is now level with the ply. Will glue on the final layer of ply tomorrow also.

Image

After that I'll aim to make progress with the CB case.

Mick
Completed: FB11 (Designer Evan Gatehouse)
Current Build: VG23 (Designer Jacques Mertens)

mhd
Frequent Poster
Frequent Poster
Posts: 75
Joined: Tue Feb 15, 2022 10:41 am
Location: New Mexico

Re: VG23 New Build

Post by mhd »

Did a layer of 9oz biaxial tape over the forward/aft joints on the keel. The top-left air bubble thankfully disappeared with the epoxy roller...and writing that reminds me that I didn't clean the roller and by now it will be set solid - arrgghh!

Image

Tape is cut ready for the last two external joints on the keel bottom - tomorrow I hope. Plans call for a further two layers of biaxial over the entire keel but I'll hold off on that until ready to attach to the hull. I want the keel-to-hull tape joint to be the bottom (innermost) layer.

And I also did a coat of epoxy on one side of the centreboard case.

Image

Last thing for the day was taking the electric plane to the centreboard itself to put some very basic profiling shape and taper into. Thicker on the leading edge and tapered aft and that will be enough. I'm not too concerned about getting a perfect profile as I just know I'll end up planing through to the lead underneath at some point and I am determined to avoid that. I'll post a photo of the centreboard once I've sanded it to some kind of reasonably fair shape, prior to glassing.

I need to head out of town to buy some mahogany for the centreboard structure - probably a week away, but will see if I can sneak off early next week some time. I've ordered the required cheek block to lift/lower the CB. But I'm currently thinking over more how to attach the stainless steel cheeks to the centreboard with the suggested sheave/bushings. I'll probably have a stab at cutting/drilling those next week too as I think I have enough 316L stainless left over from the chainplates. Need to tap out one of the stainless CB cheeks for a 3/8" bolt too. I've got the necessary tap/die kit in the garage but I'm a virgin as far as using it in anger for the first time goes - will be fun to at least try my hand at that also. I'm torn between metric/imperial (3/8" or 10mm bolt) - who knows where the boat may be if it ever needs replacement (but by Sod's Law it is bound to be the wrong place for whichever I choose!) so I may drill/tap both.